Coast Protection at Reculver - Options for the future

arrowOptions for the Future

The introduction of the Shoreline Management Plans formalised the process for determining the best all-round method of dealing with a coast protection problem. Firstly the best strategy (do nothing, retreat the line, hold the line or advance the line) is identified. Then the most cost-efficient way of implementing the chosen strategy is worked out.

Eight broad strategic options were drawn up, two with sub-options. These were then examined in sufficient detail to determine the technical requirements and costs of any engineering works and to assess each option's environmental impacts and economic consequences.

Option

Description

Cost

£million

Environmental

Rating

1

2


3


4A


4B



5A


5B



6



7


8

Do nothing

Retreat to Sarre Wall

Retreat to Thanet Way

Retreat to Railway line

Retreat to Railway line / Rushbourne Wall

Hold line using new sea walls

Hold the line using emergency repairs

Hold the line using rock revetments

Hold the line using beach management

Advance the line

94.9

43.5


33.7


8.4


8.1



8.5


5.0




5.2


4.9


33.2

12

14


15


20


22



18


15




26


34


21

 